Asda Hatfield

Our client required a full refurbishment of their car park, including surfacing, civils, and landscaping works. This project had to be carried out during the day due to EA restrictions. The store is a live site situated in a busy town centre; minimal disruption to the local community and trading hours was essential.

Project Key Stats

months

On-site Duration

1,200 sq/m

Total Site Area

Project Overview

Services Delivered

Objective

The project was very challenging given the constraints of the location and working hours available. We requested permission allowing us to carry out some of the work on Sunday nights minimising disruption to the store and surrounding roads. Traffic management was required throughout the project and all areas had to be heras fenced off.

We were required to adhere to the Asda working practice at all times Communication with the store manager was paramount to ensuring the project ran smoothly and was completed on time.

Delivery

It was agreed that the work would take place during the hours of 21:00 – 04:00 and would be phased over two nights. Each phase included the planning out and resurfacing of an area ensuring that there would be no impact during the day.

Traffic Management was still required as there was a 24-hour fast food outlet on the retail park. NMC Surfacing provided two traffic marshals, signage and barriers, and kept the outlet manager aware of their progress throughout the project.

A total of 1,735m2 was excavated. The planed areas were sprayed with tack coat and resurfaced and all joints were over banded before the lining was refreshed.